Nanaimo’s Third St. re-opens to traffic after infrastructure upgrade
NANAIMO — A major gateway into downtown is finally back open to vehicular and pedestrian traffic after almost a year of detours.
Traffic is moving along Third St. between Howard Ave. and Pine St. after construction began last November, part of the plan to build ‘Complete Streets’ in Nanaimo to create a safer environment for all road users.
Engineering project technologist and project manager Rob Shearer said they took advantage of the needed replacement of aging storm, water, and sewer infrastructure to add surface-level improvements as well.
“(Upgrades) included reconstructed pavement, new and upgraded sidewalks, separated cycling facilities, raised and improved pedestrian crossings, tactile warning surface indicators, renewed traffic signals, LED street lighting, landscaping, street trees, and a rain garden.”