B.C. politicians ask for audit of $3.86 billion North Shore water treatment plant
VANCOUVER — A group of local politicians from B.C.’s Lower Mainland are asking the provincial auditor general to investigate how the cost of a wastewater treatment plant could balloon to $3.86 billion.
Seven local city councillors from five jurisdictions say in a statement they are urging Michael Pickup to look into the delays and cost overruns, saying he has the jurisdiction because the province put $200 million toward the project.
The original cost of the North Shore Wastewater Treatment Plant in 2018 was $700 million and it was expected to open in 2020, but the Metro Vancouver regional district fired the contractor over construction delays in 2021.
Surrey Coun. Linda Annis, one of those asking for the audit, says the mismanagement of the megaproject is staggering, and Metro Vancouver taxpayers deserve to know how it went wrong and why they are stuck with the bill for the next 30 years.