Centre Block construction within cost, but Ottawa needs to make faster decisions: AG

Mar 27, 2023 | 8:07 AM

OTTAWA — Canada’s auditor general says the modernization of Parliament’s Centre Block is within budget so far, but the federal government needs to do a better job at making up their minds before major construction begins.

Karen Hogan warns in a report released today that if decision-making remains fragmented, it could lead to construction delays — and more costs for taxpayers.

The rehabilitation of Centre Block already comes with a price tag of up to $5 billion, and is set to be completed by 2031. 

Hogan says the government is responsible for deciding what it wants, including how many office spaces, committee rooms and security measures are needed.