Re-opening the Bastion St. Bridge was set to finish in June and will finally happen on Tuesday, July 16. (City of Nanaimo)
Bridge access

Bastion St. Bridge to re-open with new look and supports

Jul 15, 2019 | 10:10 AM

NANAIMO — A major downtown thoroughfare is opening after a construction delay.

The Bastion St. Bridge reopens Tuesday, July 16. It underwent significant upgrades to replace the bridge deck, seismic improvements and new signs for tourists.

The project started in May and was to last until June 28.

It was announced on June 28 the construction would take longer than anticipated, due to the bridge deck being shallower than show in historical records.