Difficult work begins to fix washed out roads after serious flooding
NANAIMO — Repairing the damage done by heavy rains and flooding Sunday and Monday won’t be an easy fix.
Mike Pearson, the Vancouver Island district manager of transportation, said they’ll have to completely rebuild a section of Rumming Rd. in Lantzville which washed away.
“It’s about a 12-metre hole that’s been created, so to fix that is going to take a bit of time.” He expected their “head-to-toe” rebuild of the road, where the foundation is slowly and carefully built back up, will take four-to-six weeks to finish.
It will be an even longer fix for the damage to Melrose Rd. in Whiskey Creek.