Partial re-opening signals home stretch of lengthy Albert St. project
NANAIMO — A significant initiative to enhance non-vehicular movement between Harewood and Nanaimo’s downtown is substantially complete.
James Knight, capital project management specialist with the City of Nanaimo, said the ongoing Albert St. Complete Street project hit a significant milestone with alternating traffic opening on the street between Pine and Kennedy St. on Friday, Nov. 24.
Due to a narrowing construction window due to weather, Knight said final asphalt and pavement work will have to wait until next spring.
“The contractor’s been working really hard to get the retaining wall in and widen the road area so that we can install the bike lanes and sidewalks on both sides, we also have some street-lighting in,” Knight told NanaimoNewsNOW.