Re-paving & safety changes to Hwy. 19A substantially complete
NANAIMO — Crews on site of paving and other upgrades along Hwy. 19A in the city’s north end are almost done.
The Ministry of Transportation told NanaimoNewsNOW work is “approximately 95 per cent complete” on the project, which saw a new road surface laid down, replacement of the vegetated median with a concrete barrier and other safety improvements.
Work extended along Hwy. 19A from Mary Ellen Dr., south to Turner Rd. where it met with a stretch of the highway which was re-done in 2020.
“Most of the work occurred at night so daytime traffic was not impacted,” a spokesperson for the ministry said. “There were minor detours in place some nights to accommodate work crews.”