Developers cancel long-delayed, $8B Atlantic Coast Pipeline
RICHMOND, Va. — The developers of the long-delayed, $8 billion Atlantic Coast Pipeline announced the cancellation of the multi-state natural gas project Sunday, citing uncertainties about costs, permitting and litigation.
Despite a victory last month at the United States Supreme Court over a critical permit, Dominion Energy and Duke Energy said in a news release that “recent developments have created an unacceptable layer of uncertainty and anticipated delays” for the 600-mile (965-kilometre) project designed to cross West Virginia and Virginia into North Carolina.
The companies said a recent pair of court rulings that have thrown into question a permitting program used around the nation to approve oil and gas pipelines and other utility work through wetlands and streams presented “new and serious challenges.”
“This new information and litigation risk, among other continuing execution risks, make the project too uncertain to justify investing more shareholder capital,” the news release said.